The Client, Voyager Express, needed to relocate their fleet and operations to a recently acquired 14-acre brownfield site that would allow them to have greater highway visibility, expansion capabilities, additional rent income and future development opportunities.

Assignment Highlights

  • Voyager2Managed the design and engineering process on a 14-acre brownfield site.
  • Built state of the art maintenance facility, new office environment, drivers lounge and fleet parking.
  • Detailed tracking of the project provide for multiple cost savings, which included re-specifying and re-bidding the methane mitigation system.

Results

  • The project, which was successfully completed, including design, entitlement and construction within the twelvemonth period that was targeted for relocation.
  • Pursued and received economic incentives in tax reimbursements from Adams County which resulted in cost savings to Client of $42,000.
  • Located construction materials below their market value after the project budget was completed, resulting in an additional cost savings of approximately $25,000 to the Client.
  • By re-specifying and rebidding the methane mitigation system, the Client saved approximately $32,000.